Dallas Logo
File #: 23-1290    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/4/2023 In control: Water Utilities Department
On agenda: 6/28/2023 Final action:
Title: Authorize an increase in the construction services contract with Estrada Concrete Company, LLC for additional work associated with wastewater main installations at two locations - Not to exceed $782,258.00, from $9,001,454.00 to $9,783,712.00 - Financing: Coronavirus State and Local Fiscal Recovery Fund ($395,808.00), Wastewater Capital Improvement F Fund ($251,339.76), and Street and Alley Improvement Fund ($135,110.24)
Indexes: 8
Attachments: 1. Maps, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 28, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Water Utilities Department
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Estrada Concrete Company, LLC for additional work associated with wastewater main installations at two locations - Not to exceed $782,258.00, from $9,001,454.00 to $9,783,712.00 - Financing: Coronavirus State and Local Fiscal Recovery Fund ($395,808.00), Wastewater Capital Improvement F Fund ($251,339.76), and Street and Alley Improvement Fund ($135,110.24)

Body
BACKGROUND

On June 23, 2021, the City Council authorized a contract with Estrada Concrete Company, LLC, for the installation of water and wastewater mains at 14 locations by Resolution No. 21-1141. During construction, unforeseen hard rock was encountered requiring a special excavator in the easement east of University Hills Boulevard from Runyon Creek Green Belt to University Hills Boulevard. In addition, after award of the construction contract it was determined that a new wastewater main was necessary within Timberloam Drive to extend service as part of the Unserved Areas Program. The original contract only included replacement of the existing water main in Timberloam Drive from St. Augustine Drive west.

This action will authorize Change Order No. 1 to the construction services contract with Estrada Concrete Company, LLC for additional work associated with wastewater main installations in the easement east of University Hills Boulevard and in Timberloam Drive. The wastewater extension in Timberloam will include approximately 1,200 feet of 8-inch diameter wastewater main utilizing ARPA Funds designated to extend water and wastewater services to unserved areas. The change order will also add contract days to account for delays outside of the contractor's control including ch...

Click here for full text