Dallas Logo
File #: 24-1896    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/31/2024 In control: Water Utilities Department
On agenda: 6/26/2024 Final action:
Title: Authorize settlement in lieu of proceeding further with condemnation in the condemnation suit styled City of Dallas v. TES-BIG RACK RANCH, INC., et al, for acquisition from TES-BIG RACK RANCH, INC., et al., of approximately 225,781 square feet of land located in Kaufman County, Texas for the Lake Tawakoni 144-inch Raw Water Transmission Pipeline Project - Not to exceed $425,548.00, increased from $30,452.00 ($26,952.00 plus closing costs and title expenses not to exceed $3,500.00) to $456,000.00 ($450,000.00, plus closing costs and title expenses not to exceed $6,000.00) - Financing: Water Construction Fund ($142,350.00), Water Capital Improvement F Fund ($283,198.00)
Indexes: 200
Attachments: 1. Map, 2. Resolution, 3. Exhibit A
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 26, 2024
COUNCIL DISTRICT(S): Outside City Limits
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize settlement in lieu of proceeding further with condemnation in the condemnation suit styled City of Dallas v. TES-BIG RACK RANCH, INC., et al, for acquisition from TES-BIG RACK RANCH, INC., et al., of approximately 225,781 square feet of land located in Kaufman County, Texas for the Lake Tawakoni 144-inch Raw Water Transmission Pipeline Project - Not to exceed $425,548.00, increased from $30,452.00 ($26,952.00 plus closing costs and title expenses not to exceed $3,500.00) to $456,000.00 ($450,000.00, plus closing costs and title expenses not to exceed $6,000.00) - Financing: Water Construction Fund ($142,350.00), Water Capital Improvement F Fund ($283,198.00)

Body
BACKGROUND

This item authorizes settlement for the acquisition from TES-BIG RACK RANCH, INC., et al., of approximately 225,781 square feet of land located in Kaufman County, Texas for the Lake Tawakoni 144-inch Raw Water Transmission Pipeline Project. This settlement will allow acquisition of the property without further condemnation proceedings.
This acquisition is part of the right-of-way required to construct approximately 32 miles of pipeline from Lake Tawakoni to the Interim Balancing Reservoir located in Terrell, TX and then to the Eastside Water Treatment Plant located in Sunnyvale, TX. The new raw water pipeline will augment the existing 72-inch and 84-inch pipelines. The construction of this pipeline will give Dallas Water Utilities the ability to utilize the full capacity of both the Lake Tawakoni and the Lake Fork raw water supply to meet future water demands.

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On August 12, 2015, the City Council authorized the acquisition, including the exercise of the right...

Click here for full text