Authorize a construction services contract for the 36-Month Bridge Maintenance, Repair, and Improvement Program for fiscal years 2027-29, which includes bridge deck and structural repairs and replacement, railing and bearing work, superstructure and substructure retrofits, foundation repairs, bank stabilization, stream channel improvements, and scour countermeasures – Ragle, Inc., lowest responsible bidder of three – Not to exceed $16,618,890.83 – Financing: Street and Alley Improvement Fund (subject to annual appropriations)
*In alignment with Infrastructure Management Plan.
Body
BACKGROUND
The existing contract for the on-call maintenance and repair of public bridges throughout the City is scheduled to expire on September 30, 2027.
The following chart illustrates Ragle, Inc.’s contractual activities with the City of Dallas for the past three years:
AVI DWU PKR TPW
Active Projects|9 9 9 9 10|Projects Completed |9 9 9 910|Change Orders|9 9 9 9 10|Projects Requiring Liquidated Damages|9 9 9 9 10|Projects Completed by Bonding Company|9 9 9 9 10|
This action will authorize a construction services contract with Ragle, Inc. for the 36-Month Bridge Maintenance, Repair, and Improvement Program for FYs 2027-2029. The scope of work will consist of full and partial-depth bridge deck repair, concrete structure repair, guard fence, vehicle and pedestrian railing construction, full deck replacement, bearing resetting and replacement, superstructure and substructure retrofitting, foundation repair, bank stabilization, stream channel improvements, and scour countermeasure construction.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction January 2027
Complete Construction January 2030
PRIOR ACTION/REVIEW (COUNCI...
Click here for full text