Authorize a construction services contract for the construction of the Trinity Strand Hi-Line Span Project, a new pedestrian bridge at the end of Hi Line Drive in the Dallas Design District, to connect the new Circuit Trail and the Katy Trail to the Trinity Strand Trail - The Fain Group, Inc., lowest responsible bidder of six - Not to exceed $8,790,898.00 - Financing: Design District TIF Fund
Body
BACKGROUND
The City of Dallas advertised for bids for the Trinity Strand Hi-Line Span Project on August 28, 2024 and September 4, 2024. In response to the advertisement, the Office of Procurement Services received bids from six firms on October 18, 2024.
This action will award a contract for construction of the Trinity Strand Hi-Line Span Bridge and Trail Project to the Fain Group, Inc., lowest responsible bidder of six, for the Base Bid and Alternate Nos. 2 and 3, in an amount not to exceed $8,790,898.00. This project is funded by the Office of Economic Development.
The scope of work includes a new prefabricated pedestrian bridge at Irving Boulevard, a custom pedestrian art bridge at the end of Hi Line Drive in the Dallas Design District, concrete trail, retaining wall, lookout plaza and development including shade structures, lighting, and landscaping at Hi-Line Drive.
The following chart illustrates The Fain Group, Inc.'s contractual activities with the City of Dallas for the past three years:
AVI DWU PKR TPW
Projects Completed|9 9 99 10|Change Orders|9 9 9| 11 1
Active Projects|9 9||9 9| 1 2
Projects Requiring Liquidated Damages|9 9||9 9| 0 0
Projects Completed by Bonding Company|9 9||9 9| 0 0
ESTIMATED SCHEDULE OF PROJECT
Begin Construction April 2025
Complete Construction ...