STRATEGIC PRIORITY: Sustainable
AGENDA DATE: September 24, 2025
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize Supplemental Agreement No. 1 to the construction services contract with Satterfield and Pontikes Construction, Inc., to include a deicing structure and an X-Charge C7 charger for electric vehicles for the Dallas Love Field Aircraft Rescue and Firefighting Station No. 21 and Operations Building Project and to extend the contract term until March 31, 2026 - Not to exceed $1,573,483.00, from $30,833,255.00 to $32,406,738.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund
Body
BACKGROUND
Dallas Love Field Airport's existing Aircraft Rescue and Firefighting Station No. 21 is located near the north side of airfield and currently accommodates six Dallas Fire Rescue vehicles, which includes four Aircraft Rescue and Fire Fighting (ARFF) Apparatus in four pull-through bays. The building was built in the 1960's and has passed its useful life. The Department of Aviation is in the process of reconfiguring the Crossfield Taxiway Project in the middle of the airfield to comply with current Federal Aviation Administration (FAA) design standards. Based on the reconfiguration, the existing fire station does not meet the FAA response time for aircraft emergencies and consequently the proposed new fire station will need to be constructed in a new location to meet the FAA requirements.
In July 2019, a site study which included a conceptual program for the building and site, was completed by Ricondo & Associates, Inc. and was approved by the Department of Aviation. The architectural programming is in accordance with the City of Dallas, FAA and ARFF standards and requirements. This project intent is to procure a contractor to build a new facility that combines efficiency and sustainability by co-locating both ARF...