Legislation Details

File #: 26-2268A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/7/2026 In control: Department of Transportation and Public Works
On agenda: 8/12/2026 Final action:
Title: Authorize a professional services contract with STV Incorporated to provide engineering services for the design of four local streets as part of Street Reconstruction Group 24-6001 (list attached to the Agenda Information Sheet) - Not to exceed $667,829.45 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($610,618.95), Water Construction Fund ($44,526.50), and Wastewater Construction Fund ($12,684.00) *In alignment with Infrastructure Management Plan.
Indexes: 13, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR: Sustainable
AGENDA DATE: August 12, 2026
COUNCIL DISTRICT(S): 6, 13
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT

Title
Authorize a professional services contract with STV Incorporated to provide engineering services for the design of four local streets as part of Street Reconstruction Group 24-6001 (list attached to the Agenda Information Sheet) - Not to exceed $667,829.45 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($610,618.95), Water Construction Fund ($44,526.50), and Wastewater Construction Fund ($12,684.00)

*In alignment with Infrastructure Management Plan.

Body
BACKGROUND

The Request for Qualifications CIZ24-PBW-3124 was issued on October 9, 2024, for the 2024 Bond Program Capital Improvement Projects. The consulting firm, STV Incorporated, was selected following the qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

This action will authorize a professional services contract with STV Incorporated for the engineering design of four local streets as part of Street Reconstruction Group 24-6001. The street reconstruction projects will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, possible replacement of drainage system, and water and wastewater improvements.

Project Council District

3000 Storey Lane from Overlake Drive |910|to Brockbank Drive

3500 Poquita Drive from El Rito Drive |910| to Bolivar Drive

3500-3600 Espanola Drive from Larga Drive |910|to Marsh Lane

8900-9000 Turtle Creek Boulevard from 13
Chevy Chase Avenue to Park Lane

ESTIMATED SCHEDULE OF PROJECT

Begin Design September 2026
Complete Design December 2027
Begin Construction July 2028
Complete Construction July 2030

PRIOR ACTION/REVIEW (COUNCIL, BOARD...

Click here for full text