File #: 25-2671A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/28/2025 In control: Department of Transportation and Public Works
On agenda: 9/24/2025 Final action:
Title: Authorize Supplemental Agreement No. 10 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of the Bridge Management Program in support of the Infrastructure Management Plan, to provide engineering and construction inspection services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges - Not to exceed $351,000.00, from $2,033,921.00 to $2,384,921.00 - Financing: General Fund
Indexes: Citywide
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Sustainable
AGENDA DATE: September 24, 2025
COUNCIL DISTRICT(S): Citywide
DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 10 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of the Bridge Management Program in support of the Infrastructure Management Plan, to provide engineering and construction inspection services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges - Not to exceed $351,000.00, from $2,033,921.00 to $2,384,921.00 - Financing: General Fund

Body
BACKGROUND


From September 23, 2020 to September 11, 2024, the City Council has authorized five Council Resolutions associated with this project, consisting of reviewing of the existing bridge conditions, development of repair costs for selected bridges, development of a list of bridges to receive design and repairs, inspections and preparation of plans, design and construction on minor bridge repair projects, monitoring on multiple bridges, as well as extending the contract for an additional year from November 5, 2024 to October 12, 2025.

This action will authorize the Supplemental Agreement to continue with the development of the Bridge Management Program in support of the Infrastructure Management Plan, to provide engineering and construction inspection services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges.

ESTIMATED SCHEDULE OF PROJECT

Began Design September 2022
Complete Design March 2026






PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On September 23, 2020, the City Council authorized an engineering services contract with Wiss Janney, Elstner Associates, Inc. to develop a Bridge Management Program in support of the Infrastructure Management Plan consisting of re...

Click here for full text