File #: 21-1443    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/30/2021 In control: Department of Public Works
On agenda: 9/22/2021 Final action:
Title: Authorize a professional services contract with SE3, LLC for the engineering design of Lemmon Avenue East from Lemmon Avenue East to Oak Grove Avenue - Not to exceed $234,022.85 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($180,012.05) and Water Construction Fund ($54,010.80)
Indexes: 14
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 22, 2021
COUNCIL DISTRICT(S): 14
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a professional services contract with SE3, LLC for the engineering design of Lemmon Avenue East from Lemmon Avenue East to Oak Grove Avenue - Not to exceed $234,022.85 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($180,012.05) and Water Construction Fund ($54,010.80)

Body
BACKGROUND

The Request for Qualifications (CIZ1721) was issued on May 31, 2018 for the 2017 Bond Projects. The consulting firm, SE3, LLC was selected following a qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

This action will authorize a professional services contract with SE3, LLC for the engineering design of Lemmon Avenue East from Lemmon Avenue East to Oak Grove Avenue. The street reconstruction thoroughfare will include replacing the existing deteriorating concrete street with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, pavement markings, water and storm drainage improvements.

SE3, LLC is a registered vendor with the City of Dallas, and their current corporate headquarters are located in Kansas City, Missouri.

ESTIMATED SCHEDULE OF PROJECT

Begin Design October 2021
Complete Design July 2022
Begin Construction December 2022
Complete Construction December 2023



PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Fund
FY 2021
FY 2022
Future Years
Street and Transportation (A) Fund (2017 General Obligation Bond Funds)
$180,012.05
$0.00
$ 0.00
Water Construction Fund
$ 54,010.80
$0.00
$0.00
Total
$234,022.85
$0.00
$0.00

M/WBE INFORMATION

In accordance with the City's Business Inclusion and Development Policy adopted on Se...

Click here for full text