File #: 24-3399    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 10/28/2024 In control: Department of Transportation and Public Works
On agenda: 12/11/2024 Final action:
Title: Authorize an increase in the construction services contract with Jeske Construction Company, to add the wastewater main improvements and appurtenance adjustments needed on Alley Reconstruction Group 17-8003 - Not to exceed $329,819.00, from $1,792,675.00 to $2,122,494.00 - Financing: Wastewater Capital Improvement G Fund ($305,739.00) and Wastewater Construction Fund ($24,080.00)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: December 11, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Jeske Construction Company, to add the wastewater main improvements and appurtenance adjustments needed on Alley Reconstruction Group 17-8003 - Not to exceed $329,819.00, from $1,792,675.00 to $2,122,494.00 - Financing: Wastewater Capital Improvement G Fund ($305,739.00) and Wastewater Construction Fund ($24,080.00)

Body
BACKGROUND

On January 10, 2024, the City Council authorized the construction services contract with Jeske Construction Company, for the construction of Alley Reconstruction Group 17-8003 by Resolution No. 24-0118.

During construction, it was discovered that it was necessary to replace the existing 6-inch wastewater main in the alley between Freeland Way and Homeway Circle and Babalos Lane with a new 8-inch wastewater main.

This action will authorize Change Order No. 1 to the construction services contract with Jeske Construction Company, to add the wastewater main improvements and appurtenance adjustments needed on Alley Reconstruction Group 17-8003 to the contract.

ESTIMATED SCHEDULE OF PROJECT

Began Construction July 2024
Complete Construction April 2025

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On January 10, 2024, the City Council authorized the construction services contract with Jeske Construction Company for the construction of Alley Reconstruction Group 17-8003, by Resolution No. 24-0118.

FISCAL INFORMATION

Fund
FY 2025
FY 2026
Future Years
Wastewater Capital Improvement G Fund
$305,739.00
$0.00
$0.00
Wastewater Construction Fund
$ 24,080.00
$0.00
$0.00
Total
$329,819.00
$0.00
$0.00

Construction Contract $1,792,675.00
Change Order No. 1 (this acti...

Click here for full text