File #: 24-82    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 12/21/2023 In control: Department of Public Works
On agenda: 5/22/2024 Final action:
Title: Authorize Supplemental Agreement No. 2 to the professional services contract with Nathan D. Maier Consulting Engineers, Inc. to provide additional engineering services for Marsalis Avenue Bridge over Cedar Creek/Dallas Zoo Bridge Repair in Bridge Repair Group 17-0001 - Not to exceed $324,905.00, from $256,665.00 to $581,570.00 - Financing: 2023 Certificate of Obligation Fund
Indexes: 4
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: May 22, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 2 to the professional services contract with Nathan D. Maier Consulting Engineers, Inc. to provide additional engineering services for Marsalis Avenue Bridge over Cedar Creek/Dallas Zoo Bridge Repair in Bridge Repair Group 17-0001 - Not to exceed $324,905.00, from $256,665.00 to $581,570.00 - Financing: 2023 Certificate of Obligation Fund

Body
BACKGROUND

The City Council authorized a professional services contract with Nathan D. Maier Consulting Engineers, Inc. to provide engineering design for the repair of the four bridges in Bridge Repair Group 17-0001.

During design, the consultant prepared a condition assessment of the Marsalis Avenue Bridge. In the condition assessment the consultant recommended a complete replacement of the bridge superstructure or a complete replacement of the bridge. It was determined that a bridge replacement is necessary due to the bridge's age, deterioration, increasing maintenance needs, and impact to the surrounding properties. The consultant needed to perform preliminary engineering services required to complete the 2025 Federal Highway Administration's Bridge Investment Program application for funding consideration.

This action will authorize Supplemental Agreement No. 2 to the professional services contract with Nathan D. Maier Consulting Engineers, Inc. to provide additional engineering services for Marsalis Avenue Bridge over Cedar Creek/Dallas Zoo Bridge Repair in Bridge Repair Group 17-0001.

If this action is delayed or deferred, it will delay the completion of preliminary engineering design and the submission of the Bridge Investment Program application, which may result in the loss of potential funding.



ESTIMATED SCHEDULE OF P...