Dallas Logo
File #: 24-2485    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 8/7/2024 In control: Dallas Water Utilities Department
On agenda: 10/8/2024 Final action:
Title: Authorize a construction services contract for the installation of water and wastewater mains and extension of water and wastewater mains to unserved areas at 21 locations (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $12,849,656.60 - Financing: Water Capital Improvement F Fund ($2,000,000.00), Water Construction Fund ($2,127,690.46), Wastewater Capital Improvement F Fund ($2,718,488.81) and ARPA Redevelopment Fund ($6,003,477.33)
Indexes: 1, 200, 4, 6, 7, 8
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: October 8, 2024
COUNCIL DISTRICT(S): 1, 4, 6, 7, 8, Outside
DEPARTMENT: Dallas Water Utilities Department
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the installation of water and wastewater mains and extension of water and wastewater mains to unserved areas at 21 locations (list attached to the Agenda Information Sheet) - Douglas Dailey Construction, LLC, lowest responsible bidder of four - Not to exceed $12,849,656.60 - Financing: Water Capital Improvement F Fund ($2,000,000.00), Water Construction Fund ($2,127,690.46), Wastewater Capital Improvement F Fund ($2,718,488.81) and ARPA Redevelopment Fund ($6,003,477.33)

Body
BACKGROUND

This action will authorize a construction services contract with Douglas Dailey Construction, LLC for the installation and extension of approximately 21,934 feet of water and wastewater mains at 21 locations, including 13 unserved areas. The extensions and installations include approximately 373 feet of 6-inch, 8,086 feet of 8-inch, and 315 feet of 12-inch diameter water mains and approximately 13,160 feet of wastewater mains. To improve equity and provide service to all residents, Dallas established the Unserved Areas program in Fiscal Year 2020-21. The goal of the unserved area program is to extend service to parts of Dallas that currently do not have accessible water and/or wastewater mains. Priority is given to areas and neighborhoods that are already occupied and where extending services benefits existing residents.

In addition to the unserved area extensions, the construction contract includes the installation and replacement of existing water mains that have reached the end of their useful life, provisions for water and wastewater emergency main replacements to support DWU operations, and the establishment of prices for fire hydrant installations ...