File #: 25-471A    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 1/24/2025 In control: Department of Transportation and Public Works
On agenda: 2/26/2025 Final action:
Title: Authorize an increase to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009 - Not to exceed $187,750.00, from $2,370,432.75 to $2,558,182.75 - Financing: Water Capital Improvement G Fund ($136,500.00), Wastewater Capital Improvement G Fund ($51,250.00)
Indexes: 4
Attachments: 1. Maps, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 26, 2025
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize an increase to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009 - Not to exceed $187,750.00, from $2,370,432.75 to $2,558,182.75 - Financing: Water Capital Improvement G Fund ($136,500.00), Wastewater Capital Improvement G Fund ($51,250.00)

Body
BACKGROUND

On June 14, 2023, the City Council authorized the construction services contract with HD Way Concrete Service, LLC for the construction of Street Reconstruction Group 17-4009, by Resolution No. 23-0781.

During construction, it was discovered that in order to complete the proposed storm drainage construction on Montague Avenue, it was necessary to clear the conflicting water and wastewater main lines encountered. This will require adding the additional water and wastewater main improvements needed to the contract.

This action will authorize Change Order No. 5 to the construction services contract with HD Way Concrete Service, LLC for the additional water and wastewater main improvements needed for Street Reconstruction Group 17-4009.

ESTIMATED SCHEDULE OF PROJECT

Began Construction October 2023
Complete Construction July 2025

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On June 14, 2023, the City Council authorized a construction services contract with HD Way Concrete Service, LLC for the construction of Street Reconstruction Group 17-4009, by Resolution No. 23-0781.

On April 24, 2024, the City Council authorized Change Order No. 1 to the construction services contract with HD Way Concrete Service, LLC for the additional water adjustments and wastewater main improvements needed on Stree...