Title: Authorize a professional services contract with Ardurra Group, Inc. to provide engineering services for the design of Arterial Street Reconstruction 1500 - 1600 Market Center Boulevard from North Riverfront Boulevard to Oak Lawn Avenue - Not to exceed $562,598.50 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($539,993.50) and Water Capital Improvement G Fund ($22,605.00) *In alignment with Infrastructure Management Plan.
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR: Sustainable
AGENDA DATE: August 12, 2026
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT

Title
Authorize a professional services contract with Ardurra Group, Inc. to provide engineering services for the design of Arterial Street Reconstruction 1500 - 1600 Market Center Boulevard from North Riverfront Boulevard to Oak Lawn Avenue - Not to exceed $562,598.50 - Financing: Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($539,993.50) and Water Capital Improvement G Fund ($22,605.00)

*In alignment with Infrastructure Management Plan.

Body
BACKGROUND

The Request for Qualifications CIZ24-PBW-3124 was issued on October 9, 2024, for the 2024 Bond Program Capital Improvements Projects. The consulting firm, Ardurra Group, Inc. was selected following the qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

This action will authorize a professional services contract with Ardurra Group, Inc. for the engineering design of Arterial Street Reconstruction 1500 - 1600 Market Center Boulevard from North Riverfront Boulevard to Oak Lawn Avenue. The street reconstruction project will include replacing the existing deteriorating concrete streets with reinforced concrete pavement, curb, gutter, sidewalk, driveway approaches, possible replacement of drainage system, and water and wastewater improvements.

ESTIMATED SCHEDULE OF PROJECT

Begin Design September 2026
Complete Design January 2028
Begin Construction September 2028
Complete Construction September 2031



PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Fund
FY 2026
FY 2027
Future Years
Street and Transportation (A) Fund (2024 General Obligation Bond Fund)
$539,993.50
$0.00
$0.00
Water Capital Improvement G Fu...