PILLAR: Sustainable
AGENDA DATE: June 24, 2026
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize Supplemental Agreement No. 3 to the professional services contract with Bridgefarmer & Associates, Inc. to provide additional engineering services for South Ewing Avenue from Interstate Highway 35 East (IH-35E) to East Clarendon Drive, and East Clarendon Drive from South Ewing Avenue to Upton Street - Not to exceed $282,660.00, from $1,460,561.20 to $1,743,221.20 - Financing: 2024B Certificates of Obligation Fund ($261,060.00) and Water Capital Improvement G Fund ($21,600.00)
*In alignment with Infrastructure Management Plan.
Body
BACKGROUND
This project will widen South Ewing Avenue from Interstate Highway 35 East (IH-35E) to East Clarendon Drive from a two-lane undivided roadway to a four-lane undivided roadway with concrete pavement, curb and gutter, sidewalks, bicycle facilities, drainage, water and wastewater utilities, and raise the bridge two feet above the 100-year base flood elevation of Cedar Creek.
This project will also reconstruct East Clarendon Drive from South Ewing Avenue to Upton Street with new concrete pavement, curb and gutter, sidewalks, drainage, water and wastewater utilities, and raise the bridge two feet above the 100-year base flood elevation of Cedar Creek.
On April 10, 2019, the City Council authorized a professional services contract with Bridgefarmer & Associates, Inc., to provide engineering design of a thoroughfare improvement project on South Ewing Avenue from Interstate Highway 35E to East Clarendon Drive by Resolution No.19-0493.
During the design of the Ewing Avenue project, a drainage study and analysis was performed to determine the necessary drainage improvements near the intersection of Ewing Avenue and Clarendon Drive. The study concluded that the intersection was bel...
Click here for full text