Dallas Logo
File #: 23-154    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/22/2022 In control: Department of Public Works
On agenda: 2/22/2023 Final action:
Title: Authorize Supplemental Agreement No. 6 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of a Bridge Management Program in support of the Infrastructure Management Plan, provide design and construction services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges - Not to exceed $500,000.00, from $792,921.00 to $1,292,921.00 - Financing: Street and Alley Improvement Fund
Indexes: 100
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 22, 2023
COUNCIL DISTRICT(S): All
DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 6 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of a Bridge Management Program in support of the Infrastructure Management Plan, provide design and construction services on minor bridge repair projects; and provide inspection and monitoring on multiple bridges - Not to exceed $500,000.00, from $792,921.00 to $1,292,921.00 - Financing: Street and Alley Improvement Fund

Body
BACKGROUND

The original professional services agreement with Wiss, Janney, Elstner Associates, Inc. began the development of a Bridge Management Program in support of the Infrastructure Management Plan (IMP) and to provide design and construction services on minor bridge repair projects. This contract was also amended through Council Resolutions and Administrative Actions to address design and construction phase services for three emergency bridge repairs that were identified through the Texas Department of Transportation (TxDOT) Bridge inspection program.

The original Bridge Management Plan identified 240 bridges needing additional inspections having a TxDOT Critical Rating of 6 or less. Due to budgetary constraints, 67 bridges were inspected in the first year with plans to address the remaining bridges in future years. Moving forward, the program will inspect an additional 60 to 70 bridges a year until all bridges have been evaluated. This is the third year of the program.

This action will authorize Supplemental Agreement No. 6 to the engineering contract with Wiss, Janney, Elstner Associates, Inc. to continue with the development of the Bridge Management Program in support of the IMP, provide design and construction services on minor b...