STRATEGIC PRIORITY: Sustainable
AGENDA DATE: August 27, 2025
COUNCIL DISTRICT(S): 2, 13, 14
DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for the complete reconstruction of traffic signals at the following five locations: Lemmon Avenue at Lomo Alto Drive, Lemmon Avenue at Wycliff Avenue, Lemmon Avenue at Manor Way, Lemmon Avenue at Inwood Road, and Lemmon Avenue at Hudnall Street; and partial reconstruction of traffic signals at the following two locations: Lemmon Avenue at Turtle Creek Boulevard and Lemmon Avenue at Haggar Way - EAR Telecommunications, LLC DBA: EARTC, lowest responsible bidder of two - Not to exceed $4,700,074.00 - Financing: Lemmon Ave from NW Hwy to US75 CMAQ AFA Fund ($2,000,000.00), Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($1,850,302.92), and ARPA Redevelopment Fund ($849,771.08)
Body
BACKGROUND
On January 25, 2023, the City Council authorized an Advance Funding Agreement (AFA) with the Texas Department of Transportation (TxDOT) to accept a federal grant from the Congestion Mitigation and Air Quality Improvement Program in the amount of $2,000,000.00 as federal share in the total project cost of $2,619,446.00 (federal share $2,000,000.00, indirect state $94,446.00, and the City of Dallas participation $525,000.00 of which $30,000.00 is to be paid to TxDOT prior to construction) for cost related to the reconstruction and upgrade of signals/equipment and construction of pedestrian improvements at the following seven intersections: Lemmon Avenue and Manor Way, Lemmon Avenue and Haggar Way, Lemmon Avenue and Inwood Road, Lemmon Avenue and Hudnall Street, Lemmon Avenue and Lomo Alto Drive, Lemmon Avenue and Turtle Creek Boulevard, and Lemmon Avenue and North Central Expressway (US 75) by Resolution No. 23-0180.
On April 10, 2024, the City Council auth...
Click here for full text