PILLAR: Growing
AGENDA DATE: August 12, 2026
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize (1) a construction services contract to construct an integrated apron that expands existing ramp space and concrete pavement over existing grass islands; and installs electrical improvements along the full length of Taxiway Apron Paved Islands; (2) the transfer of funds in an amount not to exceed $2,081,514.00 $2,081,540.00 from the Aviation Operating Fund to the Aviation Construction Fund for the Taxiway Apron Paved Islands Project at Dallas Executive Airport; and (3) an increase in appropriations in an amount not to exceed $2,081,514.00 $2,081,540.00 in the Aviation Capital Construction Fund - Nu-Way Construction, LLC, lowest responsible bidder of two - Not to exceed $2,081,514.00 $2,081,540.00 - Financing: Aviation Construction Fund
Body
BACKGROUND
Dallas Executive Airport has identified a need to expand its existing apron by paving the current grass islands. Converting these areas to pavement will increase apron capacity, provide additional aircraft parking, and improve the efficiency of aircraft maneuvering within the apron. In addition, the paved islands will enhance all-weather operational reliability by helping keep the apron, taxiways, and runways fully accessible while providing clear, well-defined routing for aircraft transitioning from the apron to the movement areas.
The ramp expansion improves service vehicle trafficability while improving pilot situational awareness and air operations safety; improves environmental quality and sustainability; and decreases overall operations airport maintenance costs.
Nu-Way Construction, LLC has had no contractual activities with the City of Dallas within the past three years.
ESTIMATED SCHEDULE OF PROJECT
Began Design February 2025
Completed Design June 2025
Begin Construction...