Title: Authorize a construction services contract for the construction of Street and Alley Petition and Target Neighborhood Group 17-1302 (list attached to the Agenda Information Sheet) - Jeske Construction Company, lowest responsible bidder of four - Not to exceed $3,379,173.00 - Financing: 2024B Certificate of Obligation Fund ($2,320,430.00), Wastewater Capital Improvement F Fund ($378,288.00), Water Capital Improvement G Fund ($644,865.00), Wastewater Construction Fund ($23,990.00), and Water Construction Fund ($11,600.00)
Indexes: 13, 14
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 26, 2024
COUNCIL DISTRICT(S): 13, 14
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of Street and Alley Petition and Target Neighborhood Group 17-1302 (list attached to the Agenda Information Sheet) - Jeske Construction Company, lowest responsible bidder of four - Not to exceed $3,379,173.00 - Financing: 2024B Certificate of Obligation Fund ($2,320,430.00), Wastewater Capital Improvement F Fund ($378,288.00), Water Capital Improvement G Fund ($644,865.00), Wastewater Construction Fund ($23,990.00), and Water Construction Fund ($11,600.00)

Body
BACKGROUND

This action will authorize a construction services contract with Jeske Construction Company for the construction of one street, three alley petition, and two target neighborhood projects as Street and Alley Petition and Target Neighborhood Group 17-1302.

The scope of this project group includes replacing the existing deteriorating streets and alleys with reinforced concrete pavement, curb and gutter, sidewalk, driveway approaches, storm drainage, water and wastewater improvements, and other miscellaneous items necessary to complete the work in accordance with plans and specifications.

The following are the locations and construction costs for each project:


Project Council District Amount

West Shore Drive from Santa Fe Trail 14 $1,670,641.00
to Alley North of Coronado Avenue

Dirk Street from Alley South of Martel Avenue 14 $ 229,753.00
to Martel Avenue

Alley between Glenleigh Drive and 13 $ 287,227.00
Manning Lane from Existing Pavement
to Manchester Drive

Alley between West Amherst Avenue and 13 $ 258,242.00
Stanford Avenue from Linwood Avenue
to Briarwood Lane

Alley between Palo Pinto Avenue and 14 $ 204,690.00
Velasco Avenue from Conch...