Dallas Logo
File #: 24-2709    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 8/23/2024 In control: Department of Aviation
On agenda: 10/23/2024 Final action:
Title: Authorize Supplemental Agreement No. 1 to the construction services contract with Flatiron Constructors, Inc. to amend the scope of work to include infrastructure for the de-icing facility at the airport, including a parking lot, shelter building and foundation, foundation for glycol equipment, and utilities for Crossfield Taxiways at Dallas Love Field - Not to exceed $3,409,841.93, from $48,618,432.00 to $52,028,273.93 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: October 23, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 1 to the construction services contract with Flatiron Constructors, Inc. to amend the scope of work to include infrastructure for the de-icing facility at the airport, including a parking lot, shelter building and foundation, foundation for glycol equipment, and utilities for Crossfield Taxiways at Dallas Love Field - Not to exceed $3,409,841.93, from $48,618,432.00 to $52,028,273.93 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund

Body
BACKGROUND

Flatiron Constructors, Inc. is providing the City of Dallas construction services to the Crossfield Taxiways at Dallas Love Field for the construction of dual parallel taxiways, designated as Taxiways F and G and planned to be perpendicular to Runways 13L-31R and 13R-31L.

This Supplemental Agreement No. 1 will amend the scope of work to include creating infrastructure for the de-icing facility at the airport, including a parking lot, shelter building and foundation, foundation for glycol equipment, and utilities for Crossfield Taxiways at Dallas Love Field.

ESTIMATED SCHEDULE OF PROJECT

Began Design October 2020
Completed Design September 2021
Began Construction August 2022
Complete Construction March 2025







PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On August 26, 2020, the City Council authorized an engineering services contract with Garver, LLC to provide design, planning, construction documents and construction administration services for the design of the Crossfield Taxiways Project at Dallas Love Field by Resolution No. 20-1216.

On June 22, 2022, the City Council authorized a construction services contract for construction services of Crossfield Taxiways Project at Dallas Love Fie...

Click here for full text