Title: Authorize (1) a Project Specific Agreement with Dallas County for funding participation of transportation-related maintenance, repairs, and improvements of Abrams Road, Greenville Avenue, Jim Miller Road and Prairie Creek Road; and (2) the receipt and deposit of funds from Dallas County in an amount not to exceed $1,666,665.00 in the General Fund - Estimated Revenue: General Fund $1,666,665.00
Indexes: 10, 5, 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: March 25, 2020
COUNCIL DISTRICT(S): 5, 8, 10
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize (1) a Project Specific Agreement with Dallas County for funding participation of transportation-related maintenance, repairs, and improvements of Abrams Road, Greenville Avenue, Jim Miller Road and Prairie Creek Road; and (2) the receipt and deposit of funds from Dallas County in an amount not to exceed $1,666,665.00 in the General Fund - Estimated Revenue: General Fund $1,666,665.00

Body
BACKGROUND

The Abrams Road, Greenville Avenue, Jim Miller Road, and Prairie Creek Road Project is a partnership project between the City of Dallas and Dallas County for transportation-related maintenance, repairs, and improvements. The City of Dallas is the lead agency responsible for administering construction of the project. This action will authorize a Project Specific Agreement with Dallas County for the transportation-related maintenance, repair, and improvements of the above-mentioned project to be performed by city contractors.

The total estimated project cost for construction is $3,333,330.00 of which $1,666,665.00 is to be funded by Dallas County, and $1,666,665.00 is to be funded by the City of Dallas.

ESTIMATED SCHEDULE OF PROJECT

Begin Construction April 2020
Complete Construction September 2020

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On December 13, 2017, City Council authorized a Master Interlocal Agreement with Dallas County pertaining to the coordination of responsibilities for transportation-related maintenance on roadways and bridges within the city of Dallas by Resolution No. 17-1892.

On November 14, 2018, City Council authorized a Project Specific Agreement with Dallas County for funding participation in the repair, maintenance, and improvemen...