File #: 23-215    Version: 1 Name:
Type: CONSENT AGENDA Status: Corrected; Approved
File created: 1/4/2023 In control: Department of Aviation
On agenda: 2/22/2023 Final action:
Title: Authorize Supplemental Agreement No. 2 to extend the term of the professional services contract with O'Brien Engineering, Inc. for (1) additional design and construction administration services for the Dallas Executive Airport Streetscape Enhancements Project; and (2) an increase in the fixed limit of the total construction budget for the project to $3,500,000.00 - Not to exceed $113,220.00, from $352,034.47 to $465,254.47 - Financing: Aviation Construction Fund
Indexes: 3
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 22, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 2 to extend the term of the professional services contract with O'Brien Engineering, Inc. for (1) additional design and construction administration services for the Dallas Executive Airport Streetscape Enhancements Project; and (2) an increase in the fixed limit of the total construction budget for the project to $3,500,000.00 - Not to exceed $113,220.00, from $352,034.47 to $465,254.47 - Financing: Aviation Construction Fund

Body
BACKGROUND

The Land Use Study for the Dallas Executive Airport approved by Dallas City Council on December 13, 2017, included recommendations for streetscape improvements around the airport property based on feedback from residents in the community. The improvements are intended to provide a more walkable neighborhood and improve pedestrian circulation to enhance pathways and bike connectivity to other City trails and recreation within the vicinity.
The scope of the original contract authorized on November 13, 2019, included the development of standards for the design and construction of sidewalks, bicycle trails, landscaping, pedestrian lighting, wayfinding signage and other related improvements for roadways immediately adjacent to the airport. The current action will provide funding for additional design to address comments from the Texas Department of Transportation and extend the contract term to cover additional scope of work.

ESTIMATED SCHEDULE OF PROJECT

Began Design December 2019
Complete Design April 2023
Begin Construction November 2023
Complete Construction November 2024



PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On November 13, 2019, City Council authorized a professional services contract with O'Brien Engine...