STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 8, 2020
COUNCIL DISTRICT(S): Outside City Limits
DEPARTMENT: Department of Sustainable Development and Construction
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
title
Authorize acquisition from Charles T. Simmons and Nan Simmons, of approximately 11,736 square feet of land improved with a manufactured dwelling located in Van Zandt County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $38,866.00 ($35,866.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund
body
BACKGROUND
This item authorizes the acquisition from Charles T. Simmons and Nan Simmons, of approximately 11,736 square feet of land improved with a manufactured dwelling located in Van Zandt County. This property will be used for the construction of a 144-inch raw water transmission line for the Lake Tawakoni 144-inch Transmission Pipeline Project. The consideration is based on an independent appraisal. The relocation benefits are estimated to be $58,000.00.
This acquisition is part of the right-of-way required to construct approximately 32 miles of pipeline from Lake Tawakoni to the Interim Balancing Reservoir located in Terrell, Texas and then to the Eastside Water Treatment Plant located in Sunnyvale, Texas. The new raw water pipeline will augment the existing 72-inch and 84-inch pipelines. The construction of this pipeline will give Dallas Water Utilities the ability to utilize the full capacity of both the Lake Tawakoni and the Lake Fork raw water supply to meet the current City needs and future water demands.
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Water Construction Fund - $38,866.00 ($35,866.00, plus closing costs and title expenses not to exceed $3,000.00)
OWNERS
Charles T. Simmons
Nan Simmo...
Click here for full text