File #: 19-1331    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/28/2019 In control: Department of Aviation
On agenda: 10/23/2019 Final action:
Title: Authorize an engineering services contract with HNTB Corporation to provide design and construction administration services for the rehabilitation of Taxiway C at Dallas Love Field - Not to exceed $3,363,326.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($2,363,326.00) and Federal Aviation Administration Airport Improvement Program Grant Funds ($1,000,000.00)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: October 23, 2019
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

Title
Authorize an engineering services contract with HNTB Corporation to provide design and construction administration services for the rehabilitation of Taxiway C at Dallas Love Field - Not to exceed $3,363,326.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($2,363,326.00) and Federal Aviation Administration Airport Improvement Program Grant Funds ($1,000,000.00)

Body
BACKGROUND

This action will authorize an engineering services contract with HNTB Corporation for the rehabilitation of Taxiway C at Dallas Love Field. The rehabilitation of Taxiway C was identified in the 2009 Applied Research Associates, Inc. Pavement Evaluation Report due to the end of its concrete pavement's useful life. The rehabilitation project will be divided into two phases as follows: Phase I from Taxiway D to Runway 31L approach and Phase II from West End of Taxiway C5 to Runway 13R end. The scope of work includes demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway C and connecting taxiways.

ESTIMATED SCHEDULE OF PROJECT

Phase - I

Begin Design November 2019
Complete Design January 2020
Begin Construction September 2020
Complete Construction February 2022





Phase - II

Begin Design January 2020
Complete Design August 2020
Begin Construction January 2023
Complete Construction May 2023

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Aviation Passenger Facility Charge - Near Term Projects Fund - $2,363,326.00
Federal Aviation Administration Airport Improvement Program Grant Funds - $1,000,000.00

Design (this action) $ 3,363,326.00
Construction (estimate) $31,993,000.00

Total Project Cost (e...