STRATEGIC PRIORITY: Sustainable
AGENDA DATE: June 11, 2025
COUNCIL DISTRICT(S): 3, 8
DEPARTMENT: Dallas Water Utilities Department
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize Supplemental Agreement No. 4 to the professional services contract with Kimley-Horn & Associates, Inc. to provide additional construction phase engineering services for the rehabilitation of the Southside Wastewater Interceptor and engineering services for wastewater improvements to serve the Red Bird redevelopment area sewershed - Not to exceed $451,740.00, from $3,155,543.00 to $3,607,283.00 - Financing: Wastewater Capital Improvement F Fund ($60,000.00) and ECO (I) Fund (2017 General Obligation Bond Funds) ($391,740.00)
Body
BACKGROUND
On September 14, 2016, the City Council authorized a contract with Kimley-Horn & Associates, Inc. for professional engineering services to design the replacement and rehabilitation of water and wastewater mains at 14 locations. The contract included approximately 16,270 feet of 8-inch through 42-inch water and wastewater mains and 25,011 feet of 54-inch through 120-inch wastewater mains, including the Southside Wastewater Interceptor Rehabilitation Project.
On February 14, 2018, the City Council authorized Supplemental Agreement No. 1 with Kimley-Horn & Associates, Inc. for the study, evaluation, recommendation, and design of wastewater infrastructure improvements in the University Hills area between Camp Wisdom Road and the Dallas-Lancaster corporate limit. Supplemental Agreement No. 2 was authorized on January 28, 2022, by Administrative Action 22-5212 to provide construction phase services for the Southside Wastewater Interceptor Rehabilitation project and easement descriptions, exhibits, environmental services, and revised plans for the University Hills water and wastewater improvements project. Supplemental Agreement No. 3 was authorized on December 7, 2022, by Administrativ...
Click here for full text