Title: Authorize an increase in the construction services contract with CCGMG LLC Series B for additional work in the alley between Edgefield Avenue and Windomere Avenue from Twelfth Street to Wentworth Street - Not to exceed $116,870.00, from $497,361.00 to $614,231.00 - Financing: Water Capital Improvement F Fund
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 22, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with CCGMG LLC Series B for additional work in the alley between Edgefield Avenue and Windomere Avenue from Twelfth Street to Wentworth Street - Not to exceed $116,870.00, from $497,361.00 to $614,231.00 - Financing: Water Capital Improvement F Fund

Body
BACKGROUND

This action will authorize Change Order No. 1 to the construction services contract with CCGMG LLC Series B for additional work at the alley located at Edgefield Avenue and Windomere Avenue from Twelfth Street to Wentworth Street. Change Order No. 1 will increase the contract amount by $116,870.00, from $497,361.00 to $614,231.00 and add a total of 30 calendar days to the contract term.

The additional scope of work includes adjustments of 26 water services for the lots located at the alley between Edgefield Avenue and Windomere Avenue from Twelfth Street to Wentworth Street. During construction, it was discovered that 26 existing water services were in conflict with the alley pavement construction. Adjustment of these water meters should be completed in a timely manner to avoid disruption of water services to property owners and minimize delays to the completion of the project.

ESTIMATED SCHEDULE OF PROJECT

Began Construction August 2022
Complete Construction May 2023

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On September 9, 2021, City Council authorized the construction services contract with CCGMC LLC Series B by Resolution No. 21-1451.

FISCAL INFORMATION

Fund
FY 2023
FY 2024
Future Years
Water Capital Improvement F Fund
$116,870.00
$0.00
$0.00

Construction $497,361.00
Change Order No. 1 (this action) $116,870.00

Total $614,231.00