Legislation Details

File #: 26-1489A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 4/22/2026 In control: Park & Recreation Department
On agenda: 5/27/2026 Final action:
Title: Authorize a construction services contract for the construction of the Campbell Green Recreation Center Renovation and Expansion Project located at 16600 Park Hill Drive - JC Commercial, Inc., best value proposer of twelve - Not to exceed $6,581,875.00 - Financing: Park and Recreation Facilities (B) Fund (2024 General Obligation Bond Fund)
Indexes: 12
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR: Vibrant
AGENDA DATE: May 27, 2026
COUNCIL DISTRICT(S): 12
DEPARTMENT: Park & Recreation Department
PRIORITY: N/A
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of the Campbell Green Recreation Center Renovation and Expansion Project located at 16600 Park Hill Drive - JC Commercial, Inc., best value proposer of twelve - Not to exceed $6,581,875.00 - Financing: Park and Recreation Facilities (B) Fund (2024 General Obligation Bond Fund)

Body
BACKGROUND

On November 12, 2025, the City of Dallas advertised a Request for Competitive Sealed Proposal (RFCSP) for the construction of the Campbell Green Recreation Center Project with bids due December 19, 2025. An in-person pre-proposal conference was held on December 9, 2025.

In response to the advertisement, the Office of Procurement Services received submittals from twelve firms on December 19, 2025. The bid procurement process complied with the City's Administrative Directive 4-05: Contracting Policy, Section 10 Procurement Processes.

The Campbell Green Recreation Center Renovation and Expansion Project is the renovation of an existing 14,468 square foot recreation building with an addition that is 6,088 square feet into an expanded 20,566 square foot recreation center that will serve the Campbell Green Park community. The renovated recreation center will include a new office suite and activity room, a fitness classroom with an expanded fitness room and a new kitchenette to serve the renovated multi-purpose room.

This action will authorize a construction services contract with JC Commercial, Inc., best value proposer of twelve, for the construction of the Campbell Green Recreation Center Renovation and Expansion Project.






ESTIMATED SCHEDULE OF PROJECT

Began Design February 2025
Completed Design November 2025
Begin Construction June 2026
Complete Construction October 2027

PRIOR ACTION/REVIEW (...

Click here for full text