STRATEGIC PRIORITY: Quality of Life
AGENDA DATE: October 27, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT
Title
Authorize a construction services contract for the construction of the Kidd Springs Park Japanese Garden renovations located at 700 West Canty Street - with C. Green Scaping, LP, lowest responsive bidder of three - Not to exceed $932,588.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Fund)
Body
BACKGROUND
On May 5, 2021 and May 12, 2021, the City of Dallas advertised for bids for Kidd Springs Park Japanese Garden Renovations. In response to the advertisement, the Office of Procurement Services received bids from three responsive firms on June 18, 2021.
This action will award a contract for construction of Kidd Springs Park Japanese Garden Renovations to C. Green Scaping, LP, lowest responsive bidder of three for the Base Bid and Alternates Nos. 1 and 2 in an amount not to exceed $932,588.00. This project was included in the 2017 Bond Program.
The scope of work includes the construction of an accessible walkway through the Japanese Garden between the recreation center and creative playground.
The following chart illustrates C. Green Scaping, LP's, contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Projects Completed |9 9 9||9 9||9 10|Active Projects |9 9 9||99||9 10|Change Orders |9 9 9||99||9 10|Projects Requiring Liquidated Damages |9 9 9||9 9||9 10|Projects Completed by Bonding Company |9 9 9||9 9||9 10|
ESTIMATED SCHEDULE OF PROJECT
Began Design April 2020
Completed Design April 2021
Begin Construction December 2021
Complete Construction June 2022
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On October 21, 2021, the Park and Recreation Board authorized a construction services contract with C. Green Scaping, LP for th...