PILLAR: Sustainable
AGENDA DATE: September 9, 2026
COUNCIL DISTRICT(S): Citywide
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize an increase in the construction services contract with Estrada Concrete Company, LLC for the additional barrier free ramp and sidewalk improvements needed for the 2024 Barrier Free Ramp Improvements along Dallas Area Rapid Transit (DART) Bus Routes – Not to exceed $980,000.00, from $38,386,700.00 to $39,366,700.00 – Financing: DART Transportation Projects Fund
*In alignment with Dallas Sidewalks Master Plan.
Body
BACKGROUND
On June 14, 2023, the City Council authorized an ILA with DART for the distribution of up to $80,000,000.00 in funding from DART which consists of the City’s portion of (i) excess sales tax funds from DART of $72,000,000.00 and (ii) additional RTC funds of approximately $8,000,000.00, all to be used to complete projects eligible for this funding that will benefit DART’s Public Transportation System or provide Complementary Transportation Services located in Dallas by Resolution No. 23-0822.
On February 16, 2024, two bids were received for the 2024 Barrier Free Ramp Improvements along DART Bus Routes, Estrada Concrete Company, LLC was selected as the lowest responsible bidder.
On March 27, 2024, the City Council authorized a twenty-two-month contract with Estrada Concrete Company, LLC, for the 2024 Barrier Free Ramp Improvements along DART Bus Routes that includes water and wastewater adjustments at various locations throughout the City, in an amount not to exceed $33,848,975.00, by Resolution No. 24-0458.
On October 1, 2024, Administrative Action No. 24-0829 authorized Change Order No. 1 to the construction services contract with Estrada Concrete Company, LLC to add several bid items necessary for the construction of barrier free ramps and the construction of a reinforced concrete ...