Type: CONSENT AGENDA Status: Approved
File created: 1/21/2025 In control: Department of Transportation and Public Works
On agenda: 2/26/2025 Final action:
Title: Authorize an increase in the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue - Not to exceed $286,347.68, from $30,061,949.00 to $30,348,296.68 - Financing: Wastewater Capital Improvement G Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: February 26, 2025
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue - Not to exceed $286,347.68, from $30,061,949.00 to $30,348,296.68 - Financing: Wastewater Capital Improvement G Fund

Body
BACKGROUND

On September 27, 2023, the City Council authorized the construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.

During construction, it was discovered that the existing clay wastewater line in Walton Street was too fragile to survive the proposed encasement work. Consequently, it is necessary to add the additional wastewater improvements needed to replace the fragile wastewater line in Walton Street to the contract.

This action will authorize Change Order No. 2 to the construction services contract with Rebcon, LLC for the additional wastewater improvements needed on Commerce Street from Good Latimer Expressway to Exposition Avenue.

ESTIMATED SCHEDULE OF PROJECT

Began Construction March 2024
Complete Construction December 2026

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On September 27, 2023, the City Council authorized the construction services contract with Rebcon, LLC for the construction of Commerce Street from Good Latimer Expressway to Exposition Avenue by Resolution No. 23-1324.

FISCAL INFORMATION

Fund
FY 2025
FY 2026
Future Years
Wastewater Capital Improvement G Fund
$286,347.68
$0.00
$0.00

Construction Contract $29,968,199.00
Change Order No. 1 $ 93,750.00
Change Order No. 2 (this action) $ 286,347.68
Total $30...