PILLAR: Sustainable
AGENDA DATE: March 25, 2026
COUNCIL DISTRICT(S): 10
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT
Title
Authorize (1) a Project Specific Agreement with Dallas County ("County") (Transportation - Major Capital Improvement Project No. 10245), in the amount of $2,000,000.00, with $1,000,000.00 (less $50,000.00 for in-house project delivery costs) as County participation for construction and $1,000,000.00 as City participation for the design and construction of transportation improvements at intersections along Walnut Hill Lane and Skillman Street, from Abrams Road to Audelia Road; (2) the increase in appropriations in an amount not to exceed $950,000.00 in the Transportation Special Projects Fund; and (3) the receipt and deposit of funds in an amount not to exceed $950,000.00 in the Transportation Special Projects Fund - Not to exceed $1,950,000.00 - Financing: Transportation Special Projects Fund ($950,000.00) and 2017 Street and Transportation (A) Fund (2017 General Obligation Bond Fund) ($1,000,000.00)
*In alignment with Infrastructure Management Plan.
Body
BACKGROUND
On July 6, 2021, the City of Dallas and Dallas County, by Commissioners Court Order 2021-0697, entered into a Master Agreement for the purpose of transportation improvements on roads inside Dallas County. The City wishes to enter into a Project Specific Agreement (PSA) with Dallas County for the design and construction of transportation improvements at intersections along Walnut Hill Lane and Skillman Street, from Abrams Road to Audelia Road, Major Capital Improvement Project No. 10245 ("Project").
The total estimated Project cost is $2,000,000.00 and is being funded from a combination of County and City funding sources, with $1,000,000.00 (less $50,000.00 for in-house project delivery costs) as County participation for construction and $1,000,000.00 as City p...