Dallas Logo
File #: 24-1859    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/29/2024 In control: Park & Recreation Department
On agenda: 6/26/2024 Final action:
Title: Authorize (1) Supplemental Agreement No. 3 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway; and (2) an increase in appropriations in the amount of $110,700.00 in the Golf Improvement Trust Fund - Not to exceed $990,900.76, from $3,270,575.00 to $4,261,475.76 - Financing: Park and Recreation Facilities Fund (2006 General Obligation Bond Fund) ($654,300.00), Golf Improvement Trust Fund ($110,700.00) and General Fund ($225,900.76)
Indexes: 10
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: June 26, 2024
COUNCIL DISTRICT(S): 10
DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize (1) Supplemental Agreement No. 3 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway; and (2) an increase in appropriations in the amount of $110,700.00 in the Golf Improvement Trust Fund - Not to exceed $990,900.76, from $3,270,575.00 to $4,261,475.76 - Financing: Park and Recreation Facilities Fund (2006 General Obligation Bond Fund) ($654,300.00), Golf Improvement Trust Fund ($110,700.00) and General Fund ($225,900.76)

Body
BACKGROUND

This action will authorize Supplemental Agreement No. 3 to the design-build contract with Phoenix I Restoration and Construction, LLC for additional construction services for the pre-design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction completion of the partially completed Paul Dyer Administration Building located at 10031 East Northwest Highway, in an amount of $990,900.76, increasing the original contract amount from $3,270,575.00 to $4,729,639.19. This supplemental agreement will extend the contract time by 185 calendar days.

The scope of services for this supplemental agreement includes: installation of finishes, glass, mechanical & electrical systems improvements, lighting in the community rooms on level 1 and the entire level 2, as well as drainage & sidewalk improvements for the building site.

ESTIMATED SCHEDULE OF PROJECT

Began Design June 2...