|
Title:
|
(26-3165A) Authorize an increase in the construction services contract with Urban Infraconstruction, LLC to (1) provide additional concrete removal of the existing driveway, pavement, sidewalk, and median for the Pearl Street at Flora Street Intersection Improvements Project; and (2) extend the contract term by 219 working days, from March 1, 2026, to December 31, 2026 - Not to exceed $318,600.07, from $1,340,917.00 to $1,659,517.07 - Financing: DART Transportation Projects Fund
|