Legislation Details

File #: 26-3313A    Version: 1 Name:
Type: ITEMS FOR INDIVIDUAL CONSIDERATION Status: Agenda Ready
File created: 10/7/2026 In control: Department of Convention and Event Services
On agenda: 11/10/2026 Final action:
Title: Authorize Discretionary Service Agreements between the City of Dallas (City) and Oncor Electric Delivery Company, LLC (Oncor) at 701 South Lamar Street, Dallas, Texas 75202 for (a) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-726 (Vault 1) for Work Order No. 21463654, for Component One of Kay Bailey Hutchison Convention Center Dallas (KBHCCD) Master Plan; (b) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-727 (Vault 2) for Work Order No. 31968623, for Component One of KBHCCD Master Plan; (c) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-728 (Vault 3) for Work Order No. 31968795, for Component One of KBHCCD Master Plan; and (d) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-729 (Vault 4) f...
Indexes: 2
Attachments: 1. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR Growing
AGENDA DATE: November 10, 2026
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Convention and Event Services
PRIORITY: Targeted Economic Growth
______________________________________________________________________
SUBJECT

Title
Authorize Discretionary Service Agreements between the City of Dallas (City) and Oncor Electric Delivery Company, LLC (Oncor) at 701 South Lamar Street, Dallas, Texas 75202 for (a) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-726 (Vault 1) for Work Order No. 21463654, for Component One of Kay Bailey Hutchison Convention Center Dallas (KBHCCD) Master Plan; (b) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-727 (Vault 2) for Work Order No. 31968623, for Component One of KBHCCD Master Plan; (c) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-728 (Vault 3) for Work Order No. 31968795, for Component One of KBHCCD Master Plan; and (d) an Oncor Pre-order agreement, in an amount not to exceed $4,429,084.57 for long lead-time equipment for vault location VC-729 (Vault 4) for Work Order No. 31968881, for Component One of the KBHCCD Master Plan – Total not to exceed $17,716,338.28 - Financing: Convention Center Capital Construction Fund

*In alignment with Kay Bailey Hutchison Convention Center Dallas Master Plan.

Body
BACKGROUND

As construction begins across various KBHCCD Master Plan components, existing Oncor electrical infrastructure on the Convention Center property must be decommissioned, relocated, or established to support expanded facilities.

Because these electrical vaults are owned and operated by Oncor, Oncor is the sole entity authorized to perform the necessary work, making them a sole-source provider consistent with their status as a regulated utility.

Oncor, in conjunction with Inspire...