File #: 26-20A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 11/17/2025 In control: Dallas Water Utilities Department
On agenda: 1/14/2026 Final action:
Title: Authorize an increase in the construction services contract with Camino Construction, LP, for storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street - Not to exceed $1,254,100.00, from $11,631,673.00 to $12,885,773.00 - Financing: Storm Drainage Management Capital Construction Fund *In alignment with Capital Improvement Program.
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR: Sustainable
AGENDA DATE: January 14, 2026
COUNCIL DISTRICT(S):|910|DEPARTMENT: Dallas Water Utilities Department
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Camino Construction, LP, for storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street - Not to exceed $1,254,100.00, from $11,631,673.00 to $12,885,773.00 - Financing: Storm Drainage Management Capital Construction Fund

*In alignment with Capital Improvement Program.

Body
BACKGROUND

On September 11, 2024, the City Council authorized a construction services contract with Camino Construction, LP for the installation of water and wastewater main improvements at 21 locations. Prior to the beginning of construction at one of the locations, Reverchon Drive from Overcrest Street to Avon Street, it was determined that storm drainage improvements were needed to alleviate flooding in the area in addition to the proposed water and wastewater main improvements. To avoid excavation of recently restored pavement and to limit disruption to the public for multiple improvement projects, it was decided to delay the water and wastewater improvements and expedite the design of storm drainage improvements. The storm drainage improvements have been designed and will be installed under the same construction contract as the water and wastewater improvements.

This action will authorize an increase in the construction services contract with Camino Construction, LP, to include the proposed storm drainage system improvements in Reverchon Drive from Mateur Street to Avon Street. Camino Construction, LP, has provided an acceptable proposal to complete the additional work. The additional cost is less than the engineer's opinion of probable cost and represents a good value for the storm drainage improvement work. The improvements include 24, 30, and 36-inch diameter...