Dallas Logo
File #: 23-545    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/9/2023 In control: Water Utilities Department
On agenda: 3/8/2023 Final action:
Title: Authorize a Reimbursement Agreement with Union Pacific Railroad Company for preliminary engineering services for the portion of the proposed expansion of the Dallas Floodway Extension Lamar Levee that impacts Union Pacific's operations, including improvements to infrastructure - Not to exceed $225,000.00 - Financing: Trinity River Corridor Project Fund (1998 General Obligation Bond Funds)
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: March 8, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Water Utilities Department
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

title
Authorize a Reimbursement Agreement with Union Pacific Railroad Company for preliminary engineering services for the portion of the proposed expansion of the Dallas Floodway Extension Lamar Levee that impacts Union Pacific's operations, including improvements to infrastructure - Not to exceed $225,000.00 - Financing: Trinity River Corridor Project Fund (1998 General Obligation Bond Funds)

body
BACKGROUND

The City of Dallas is the owner and operator of the Dallas Levee System extending from the Elm and West Forks of the Trinity River through the main stem and terminating at Interstate Highway 20. This system is regulated by the U.S. Army Corps of Engineers (USACE). In addition to regulating the Dallas Levee System, the USACE and City have been cost participating in two separate federal projects to improve the public safety of the residents and businesses that are served by this system. The City is required to own, in fee simple, all parcels related to the Dallas Levee System.

In July 2018, the Dallas Levee System flood risk management projects included in the Modified Dallas Floodway Project (DF) and the Dallas Floodway Extension (DFE) were authorized for funding under the Supplemental Appropriation in the Bipartisan Budget Act of 2018-Public Law 115-123 (PL-115-123). This information has been presented to the City Council and provided in memorandum to the City Council at major milestones since the notification by the USACE. All work associated with the design and construction of these improvements is being performed by USACE with the City serving as a technical advisor and client. An overview of the projects, federal funding and associated local requirements included in PL 115-123 are, as follows: