File #: 25-2858A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 9/29/2025 In control: Department of Transportation and Public Works
On agenda: 12/10/2025 Final action:
Title: Authorize a construction services contract for Complete Street Improvements on Columbia Avenue/Main Street, from South Beacon Street to Deep Ellum - Axis Contracting, Inc., lowest responsible bidder of six - Not to exceed $16,064,841.80 - Financing: 2024B Certificates of Obligation Fund ($9,387,852.05), Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($4,996,250.00), Bike Lane Fund ($800,000.00), Water Capital Improvement G Fund ($553,839.75), Water Construction Fund ($218,600.00), Wastewater Construction Fund ($80,300.00), and Wastewater Capital Improvement G Fund ($28,000.00) *In alignment with Infrastructure Management Plan.
Indexes: 14, 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
PILLAR: Sustainable
AGENDA DATE: December 10, 2025
COUNCIL DISTRICT(S): 2, 14
DEPARTMENT: Department of Transportation and Public Works
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for Complete Street Improvements on Columbia Avenue/Main Street, from South Beacon Street to Deep Ellum - Axis Contracting, Inc., lowest responsible bidder of six - Not to exceed $16,064,841.80 - Financing: 2024B Certificates of Obligation Fund ($9,387,852.05), Street and Transportation (A) Fund (2024 General Obligation Bond Fund) ($4,996,250.00), Bike Lane Fund ($800,000.00), Water Capital Improvement G Fund ($553,839.75), Water Construction Fund ($218,600.00), Wastewater Construction Fund ($80,300.00), and Wastewater Capital Improvement G Fund ($28,000.00)

*In alignment with Infrastructure Management Plan.

Body
BACKGROUND

This action will authorize a construction services contract with Axis Contracting, Inc. for Complete Street Improvements, including bike lanes, on Columbia Avenue/Main Street from South Beacon Street to Deep Ellum.

The scope of work will include, but not be limited to, 56 new trees and 200 pedestrian lighting poles along the Columbia/Main Project. There are also upgrades to traffic signals at seven intersections along the project limits and the installation of new traffic signals at the intersection of Main Street and Washington Avenue.

Axis Contracting, Inc. has had no contractual activities with the City of Dallas within the past three years.

ESTIMATED SCHEDULE OF PROJECT

Begin Construction April 2026
Complete Construction May 2029





PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Fund
FY 2026
FY 2027
Future Years
2024B Certificates of Obligation Fund
$ 9,387,852.05
$0.00
$0.00
Street and Transportation (A) Fund (2024 General Obligation Bond Fund)
$ 4,996,250.00
$0.00
$0.00
Bike Lane Fun...

Click here for full text