Title: Authorize a construction services contract for the construction of Target Neighborhood Group 17-4010 (list attached to the Agenda Information Sheet) - Aushill Construction, LLC, lowest responsible bidder of six - Not to exceed $1,974,420.00 - Financing: 2024B Certificates of Obligation Fund ($1,524,830.00), Wastewater Capital Improvement G Fund ($308,170.00), Wastewater Construction Fund ($9,700.00), Water Capital Improvement G Fund ($118,170.00), and Water Construction Fund ($13,550.00)
Indexes: 4
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: January 8, 2025
COUNCIL DISTRICT(S):|910|DEPARTMENT: Departmenf of Transportation and Public Works
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of Target Neighborhood Group 17-4010 (list attached to the Agenda Information Sheet) - Aushill Construction, LLC, lowest responsible bidder of six - Not to exceed $1,974,420.00 - Financing: 2024B Certificates of Obligation Fund ($1,524,830.00), Wastewater Capital Improvement G Fund ($308,170.00), Wastewater Construction Fund ($9,700.00), Water Capital Improvement G Fund ($118,170.00), and Water Construction Fund ($13,550.00)

Body
BACKGROUND

This action will authorize a construction services contract with Aushill Construction, LLC for the improvement of two streets and an alley as Target Neighborhood Group 17-4010.

The scope of this project group includes replacing the existing deteriorating streets and alley with new reinforced concrete pavement with curb and gutter, sidewalks, driveway approaches, storm drainage, water and wastewater improvements, and other miscellaneous items necessary to complete the work in accordance with plans and specifications.

The following are the locations and construction costs for each project:

Project Council District Amount

East 12th Street from Upton Street to 200 Feet |99|$959,745.00
East of Upton Street

Alley Improvement between 8th Street and Church Street |99|$370,316.00
from Interstate 35 (I-35) East Frontage Road to North
Cliff Street

Upton Street from I-35 East Frontage Road to East 12th |99|$644,359.00
Street

The following chart illustrates Aushill Construction, LLC's contractual activities with the City of Dallas for the past three years:

AVI DWU PKR TPW

Projects Completed|999910|Active Projects|999910|Change Orders|999910|Projects Requiring Liquidated D...