Legislation Details

File #: 26-3605A    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 11/3/2026 In control: Dallas Water Utilities Department
On agenda: 12/9/2026 Final action:
Title: Authorize a twenty-four-month construction services contract for pavement repairs supporting water and wastewater repair and maintenance operations of the Dallas Water Utilities Department - Estrada Concrete Company, LLC, lowest responsible bidder of five - Not to exceed $27,010,699.25 - Financing: Water Construction Fund ($12,000,000.00), Wastewater Construction Fund ($4,489,740.25), and Dallas Water Utilities Fund ($10,520,959.00) (subject to annual appropriations) *In alignment with Infrastructure Maintenance.
Indexes: Citywide
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.
PILLAR: Sustainable
AGENDA DATE: December 9, 2026
COUNCIL DISTRICT(S): Citywide
DEPARTMENT: Dallas Water Utilities Department
PRIORITY: Infrastructure
______________________________________________________________________
SUBJECT

Title
Authorize a twenty-four-month construction services contract for pavement repairs supporting water and wastewater repair and maintenance operations of the Dallas Water Utilities Department - Estrada Concrete Company, LLC, lowest responsible bidder of five - Not to exceed $27,010,699.25 - Financing: Water Construction Fund ($12,000,000.00), Wastewater Construction Fund ($4,489,740.25), and Dallas Water Utilities Fund ($10,520,959.00) (subject to annual appropriations)

*In alignment with Infrastructure Maintenance.

Body
BACKGROUND

This action will authorize pavement repairs at various locations supporting water and wastewater asset repair and maintenance operations for the Dallas Water Utilities Department. The contract will be utilized for pavement and surface repairs to streets, alleys, sidewalks, medians, parkways, parking lots, and other areas resulting from water and wastewater main and appurtenance repairs. Approval of this contract will allow for the expeditious restoration of pavement and other surfaces following the completion of water and wastewater infrastructure repairs.

The existing contract for pavement repairs is expected to be exhausted of funds in December 2026.

The following chart illustrates Estrada Concrete Company, LLC’s contractual activities with the City of Dallas for the past three years:

AVI DWU PKR TPW

Projects Completed 0 1 0 5
Active Projects 0 1 0 2
Change Orders 0 2 0 10
Projects Requiring Liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0

ESTIMATED SCHEDULE OF PROJECT

Begin Services                        January 2027
Complete Services                 January 2029

PRIOR ACTION/REVIEW (COUNCIL, BOARD...

Click here for full text