STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 22, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
title
Authorize a decrease in the construction services contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 5, to remove the construction of the traffic signal located at North Prairie Creek Road at Forney Road from the contract - Not to exceed ($312,035.00), from $1,297,982.00 to $985,947.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
body
BACKGROUND
On June 26, 2019, City Council authorized a Local Transportation Project Advance Funding Agreement with the Texas Department of Transportation (Contract No. CSJ 0918-47-244) for the design of a new bridge over the existing Union Pacific Railroad tracks on Prairie Creek Road from north of Military Parkway to north of Forney Road by Resolution No. 19-0982.
On August 14, 2019, City Council authorized a construction contract with Roadway Solutions, Inc. for traffic signal construction of Warranted Traffic Signal Installation Group 5 at the following locations: North Prairie Creek Road at Forney Road; North Prairie Creek Road at Jennie Lee Lane; West Ledbetter Drive at Joseph Hardin Drive; West Illinois Avenue at Hollywood Avenue; and West Camp Wisdom Road at Eagle Ford Drive, in an amount not to exceed $1,297,982.00, by Resolution No. 19-1105.
This action will authorize Change Order No. 1 to the construction services contract with Roadway Solutions, Inc. to decrease the funds and remove the North Prairie Creek Road at Forney Road traffic signal construction from the contract.
The current proposed design configuration for the new bridge would significantly alter the configuration of the current intersection and traffic signal located at ...