File #: 19-1204    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/9/2019 In control: Park & Recreation Department
On agenda: 9/11/2019 Final action:
Title: Authorize a construction contract for the abatement of asbestos containing materials, mold and lead-based paint at the Hall of State located at 3939 Grand Avenue in Fair Park - Horsley Specialties, Inc., lowest responsible bidder of three - Not to exceed $365,473.00 - Financing: Fair Park Improvements (C) Fund (2017 Bond Funds)
Sponsors: District 7
Indexes: 7
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Quality of Life

AGENDA DATE:                     September 11, 2019

COUNCIL DISTRICT(S):                     7

DEPARTMENT:                     Park & Recreation Department

EXECUTIVE:                     Willis C. Winters

______________________________________________________________________

SUBJECT

 

Title

Authorize a construction contract for the abatement of asbestos containing materials, mold and lead-based paint at the Hall of State located at 3939 Grand Avenue in Fair Park - Horsley Specialties, Inc., lowest responsible bidder of three - Not to exceed $365,473.00 - Financing: Fair Park Improvements (C) Fund (2017 Bond Funds)

 

Body

BACKGROUND

 

On June 21, 2019, three bids were received for the abatement of asbestos containing materials, mold and lead based paint at the Hall of State. Horsley Specialties, Inc. was selected as the lowest responsible bidder for the Base Bid and Alternate Nos. 1 and 2, in an amount not to exceed $365,473.00.

 

The scope of work includes the removal of asbestos containing materials, visible mold growth and lead based paint.

 

Horsley Specialties, Inc. has had no contractual activities with the City of Dallas in the past three years.

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Construction                                           November 2019

Complete Construction                      January 2020

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On August 15, 2019, the Park and Recreation Board authorized a construction contract with Horsley Specialties, Inc. for the abatement of asbestos containing materials, mold and lead-based paint at the Hall of State located at 3939 Grand Avenue in Fair Park.

 

FISCAL INFORMATION

 

Fair Park Improvements (C) Fund (2017 Bond Funds) - $365,473.00

 

M/WBE INFORMATION

 

In accordance with the City's Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

                                                               

Contract Amount

Category

M/WBE Goal

M/WBE%

M/WBE $

$365,473.00

Construction

25.00%

37.70%

$137,792.80

This contract exceeds the M/WBE goal.

 

PROCUREMENT INFORMATION

 

The following three bids were received and opened on June 21, 2019:

 

*Denotes the successful bidder

                                          Alter. Nos.

Bidders                     Base Bid                     1 and 2**                      Total Bid

                                          

*Horsley Specialties, Inc.                     $351,373.00                     $  14,100.00                     $365,473.00

 2110 Wall Street, Suite 500

 Garland, TX 75041

HP EnviroVision                     $413,690.00                     $  18,200.00                     $431,890.00

RNDI Companies                     $469,890.00                     $128,300.00                     $598,190.00

 

**Alternate No. 1 - provides for abatement of visible mold growth in the fan room.

**Alternate No. 2 - provides for abatement of visible mold growth in the auditorium stage crawl space.

 

OWNER

 

Horsley Specialties, Inc

 

Robert Horsley, President

Gary N. Chalk, Senior Vice President/Treasurer

Kimberly Horsley, Secretary

 

MAP

 

Attached