STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 25, 2019
COUNCIL DISTRICT(S): All
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT
Title
Authorize a construction contract for the Bond 36-Month Street Resurfacing & Street Improvements Project for the 2017 Capital Bond Program - Heritage Materials, LLC, lowest responsible bidder of three - Not to exceed $80,355,051.25 - Financing: Street and Transportation (A) Fund (2017 Bond Funds) (subject to annual appropriations)
Body
BACKGROUND
This action will authorize a construction contract with Heritage Materials, LLC, lowest responsible bidder of three, to provide construction services for the Bond 36-Month Street Resurfacing & Street Improvements Project.
This project provides for construction services scheduled for Fiscal Year 2020-2022. Bid specifications were developed and publicly advertised on June 12 and June 19, 2019, for competitive bids associated with the Bond 36-Month Street Resurfacing & Street Improvements Project. Bids were opened on June 28, 2019.
Bids were structured with a Base Bid and an Additive Alternate for the installation of Intelligent Transportation Systems Conduit in the City of Dallas’ Public Right-of-Way, but only the Base Bid is funded because of the high cost of the Additive Alternate Bid.
Heritage Materials, LLC has had no contractual activities with the City of Dallas within the past three years.
ESTIMATED SCHEDULE OF PROJECT
Begin Construction October 2019
Complete Construction October 2022
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
City Council will be briefed by memorandum regarding this matter on September 20, 2019.
FISCAL INFORMATION
Street and Transportation (A) Fund (2017 Bond Funds) - $80,355,051.25 (subject to annual appropriations)
Construction (this action) $ 80,355,051.25
Testing (Est.) $ 602,000.00
Total Project Costs $80,957,051.25
Fund |
FY 2019-20 |
FY 2020-21 |
FY 2021-22 |
Street and Transportation (A) Fund (2017 Bond Funds) |
$24,258,482.00 |
$21,316,800.00 (subject to annual appropriations) |
$34,779,769.25 (subject to annual appropriations) |
Total |
$24,258,482.00 |
$21,316,800.00 |
$34,779,769.25 |
Council District Amount
1 $ 2,122,496.53
2 $ 3,756,108.89
3 $ 3,338,464.79
4 $ 72,668.82
5 $ 1,716,389.02
6 $ 6,661,790.50
7 $ 4,661,586.64
8 $ 3,612,770.96
9 $18,816,912.18
10 $ 4,403,778.67
11 $ 2,934,761.44
12 $ 9,416,668.61
13 $10,457,910.60
14 $ 8,382,743.60
Total $80,355,051.25
The majority of bond Street Resurfacing work for Council District 4 was completed in Fiscal Years 2017-18 and 2018-19 (see chart below).
Sum of *Lane miles |
Column Labels |
|
|
|
|
|
Council District |
2018 |
2019 |
2020 |
2021 |
2022 |
Grand Total |
1 |
7.565 |
13.963 |
7.298 |
|
|
28.826 |
2 |
7.331 |
12.729 |
7.991 |
4.924 |
|
32.975 |
3 |
9.621 |
10.525 |
7.811 |
3.668 |
|
31.624 |
4 |
7.953 |
12.727 |
0.250 |
|
|
20.930 |
5 |
8.404 |
9.102 |
5.902 |
|
|
23.408 |
6 |
1.705 |
9.864 |
13.534 |
5.698 |
3.674 |
34.475 |
7 |
7.717 |
12.524 |
8.553 |
7.475 |
|
36.269 |
8 |
7.220 |
13.593 |
11.036 |
1.386 |
|
33.235 |
9 |
7.601 |
13.510 |
13.646 |
37.259 |
13.795 |
85.810 |
10 |
6.674 |
17.376 |
6.277 |
6.941 |
1.924 |
39.192 |
11 |
7.555 |
12.779 |
8.638 |
0.815 |
0.638 |
30.425 |
12 |
8.948 |
13.197 |
5.071 |
21.351 |
5.955 |
54.523 |
13 |
1.104 |
17.677 |
10.276 |
20.385 |
5.298 |
54.739 |
14 |
9.252 |
10.287 |
9.575 |
15.526 |
3.722 |
48.363 |
6, 13 |
12.692 |
|
|
|
|
12.692 |
Grand Total |
111.342 |
179.854 |
115.857 |
125.427 |
35.007 |
567.486 |
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Category |
M/WBE Goal |
M/WBE % |
M/WBE $ |
$80,355,051.25 |
Construction |
25.00% |
26.13% |
$21,000.000.00 |
• This contract exceeds the M/WBE goal. |
PROCUREMENT INFORMATION
The following three bids with quotes were received and opened on June 28, 2019:
*Denotes successful bidder
Bidders Base Bid Additive Alternate Total Bid
*Heritage Materials, LLC $80,355,051.25 $ 8,370,750.00 $ 88,725,801.25
608 Henrietta Creek Road
Roanoke, TX 76262
TexasBit $95,915,566.11 $14,836,215.50 $110,751,781.61
NPL $96,529,214.50 $16,436,850.00 $112,966,064.50
OWNER
Heritage Materials, LLC
Frank Renda, Vice President
MAP
Attached