File #: 19-1331    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 8/28/2019 In control: Department of Aviation
On agenda: 10/23/2019 Final action:
Title: Authorize an engineering services contract with HNTB Corporation to provide design and construction administration services for the rehabilitation of Taxiway C at Dallas Love Field - Not to exceed $3,363,326.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($2,363,326.00) and Federal Aviation Administration Airport Improvement Program Grant Funds ($1,000,000.00)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     October 23, 2019

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize an engineering services contract with HNTB Corporation to provide design and construction administration services for the rehabilitation of Taxiway C at Dallas Love Field - Not to exceed $3,363,326.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund ($2,363,326.00) and Federal Aviation Administration Airport Improvement Program Grant Funds ($1,000,000.00)

 

Body

BACKGROUND

 

This action will authorize an engineering services contract with HNTB Corporation for the rehabilitation of Taxiway C at Dallas Love Field. The rehabilitation of Taxiway C was identified in the 2009 Applied Research Associates, Inc. Pavement Evaluation Report due to the end of its concrete pavement’s useful life. The rehabilitation project will be divided into two phases as follows: Phase I from Taxiway D to Runway 31L approach and Phase II from West End of Taxiway C5 to Runway 13R end. The scope of work includes demolition, removal, reconstruction, realignment, and rehabilitation of Taxiway C and connecting taxiways.

 

ESTIMATED SCHEDULE OF PROJECT

 

Phase - I

 

Begin Design                     November 2019

Complete Design                     January 2020

Begin Construction                     September 2020

Complete Construction                     February 2022

 

 

 

 

 

Phase - II

 

Begin Design                     January 2020

Complete Design                     August 2020

Begin Construction                     January 2023

Complete Construction                     May 2023

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Aviation Passenger Facility Charge - Near Term Projects Fund - $2,363,326.00

Federal Aviation Administration Airport Improvement Program Grant Funds - $1,000,000.00

 

Design (this action)                     $  3,363,326.00

Construction (estimate)                     $31,993,000.00

 

Total Project Cost (estimate)                     $35,356,326.00

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$3,363,326.00

Architectural & Engineering

25.66%

29.10%

$978,860.00

This contract exceeds the M/WBE goal.

 