File #: 19-1426    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 9/10/2019 In control: Department of Public Works
On agenda: 10/23/2019 Final action:
Title: Authorize Supplemental Agreement No. 8 to the professional services contract with TranSystems Corporation for additional engineering design of parkway improvements on Main Street from Good Latimer Expressway to Exposition Avenue for the Deep Ellum Streetscape Project - Not to exceed $67,404.00, from $1,439,810.00 to $1,507,214.00 - Financing: Street and Transportation Improvements Fund (2012 Bond Funds)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: October 23, 2019
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 8 to the professional services contract with TranSystems Corporation for additional engineering design of parkway improvements on Main Street from Good Latimer Expressway to Exposition Avenue for the Deep Ellum Streetscape Project - Not to exceed $67,404.00, from $1,439,810.00 to $1,507,214.00 - Financing: Street and Transportation Improvements Fund (2012 Bond Funds)

Body
BACKGROUND

On August 27, 2008, City Council authorized a professional services contract with TranSystems Corporation for the engineering design of the Deep Ellum Streetscape Project by Resolution No. 08-2271.

This action will authorize Supplemental Agreement No. 8 to the professional services contract with TranSystems Corporation for additional engineering design of parkway improvements on Main Street from Good Latimer Expressway to Exposition Avenue for the Deep Ellum Streetscape Project.

These services will include plan view layouts that identify specific locations for parkway improvements, including necessary sidewalk and landscape repair details, as these improvements will not provide a full reconstruction of the area, but rather necessary "spot" repairs of the damaged sidewalk.

The project scope has been continually developed to accommodate additional pedestrian-oriented design concepts for the referenced segment identified by the surrounding community's desire to improve citizen safety concerns in the area, and to improve upon the original concepts.

ESTIMATED SCHEDULE OF PROJECT

Began Design September 2008
Complete Design April 2020
Begin Construction September 2020
Complete Construction March 2021

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On August 27, 200...