File #: 19-1601    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 10/9/2019 In control: Department of Public Works
On agenda: 1/8/2020 Final action: 1/8/2020
Title: Authorize a construction contract for the street reconstruction of Highland Road from Ferguson Road to Primrose Drive - Tiseo Paving Company, lowest responsible bidder of three - Not to exceed $3,996,741.65 - Financing: Street and Transportation Improvements Fund (2012 Bond Funds) ($1,410,077.05), Capital Projects Reimbursement Fund ($733,357.00), Street and Alley Improvement Fund ($500,000.00), Water Utilities Capital Improvement Funds ($1,314,772.60), and Water Utilities Capital Construction Funds ($38,535.00)
Indexes: 9
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 8, 2020
COUNCIL DISTRICT(S): 9
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction contract for the street reconstruction of Highland Road from Ferguson Road to Primrose Drive - Tiseo Paving Company, lowest responsible bidder of three - Not to exceed $3,996,741.65 - Financing: Street and Transportation Improvements Fund (2012 Bond Funds) ($1,410,077.05), Capital Projects Reimbursement Fund ($733,357.00), Street and Alley Improvement Fund ($500,000.00), Water Utilities Capital Improvement Funds ($1,314,772.60), and Water Utilities Capital Construction Funds ($38,535.00)

Body
BACKGROUND

This action will authorize a construction contract with Tiseo Paving Company for the street reconstruction of Highland Road from Ferguson Road to Primrose Drive to include upgrading a two-lane residential collector from a two-way undivided asphalt roadway to a two-way undivided concrete roadway with dedicated bike lanes, on-street parallel parking, 6-foot sidewalks, pedestrian lighting and other pedestrian enhancements. This project will also provide traffic signal modifications at Ferguson Road, landscaping, drainage improvements, and water and wastewater upgrades.

The following chart illustrates Tiseo Paving Company's contractual activities with the City of Dallas for the past three years:

PBW DWU PKR

Projects Completed 11|9910|Change Orders|99910|Projects Requiring Liquidated Damages|99910|Projects Completed by Bonding Company|99910|
ESTIMATED SCHEDULE OF PROJECT

Begin Construction April 2020
Complete Construction October 2021

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On January 10, 2001, City Council authorized a Master Agreement with Dallas County governing the Major Capital Improvement Program by Resolution No. 01-0104.

On April ...