Dallas Logo
File #: 19-1716    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 10/24/2019 In control: Department of Sustainable Development and Construction
On agenda: 1/8/2020 Final action: 1/8/2020
Title: Authorize acquisition from Garland W. Martin, of approximately 46,187 square feet of land improved with a single-family dwelling located in Hunt County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $121,442.00 ($118,442.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund
Indexes: 200
Attachments: 1. Map, 2. Resolution, 3. Exhibit A, 4. Exhibit B
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     January 8, 2020

COUNCIL DISTRICT(S):                     Outside City Limits

DEPARTMENT:                     Department of Sustainable Development and Construction

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize acquisition from Garland W. Martin, of approximately 46,187 square feet of land improved with a single-family dwelling located in Hunt County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $121,442.00 ($118,442.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund

 

body

BACKGROUND

 

This item authorizes the acquisition from Garland W. Martin, of approximately 46,187 square feet of land improved with a single-family dwelling located in Hunt County. This property will be used for the construction of a 144-inch raw water transmission line for the Lake Tawakoni 144-inch Transmission Pipeline Project. The consideration is based on an independent appraisal. There are no relocation benefits associated.

 

This acquisition is part of the right-of-way required to construct approximately 32 miles of pipeline from Lake Tawakoni to the Interim Balancing Reservoir located in Terrell, Texas and then to the Eastside Water Treatment Plant located in Sunnyvale, Texas. The new raw water pipeline will augment the existing 72-inch and 84-inch pipelines. The construction of this pipeline will give Dallas Water Utilities the ability to utilize the full capacity of both the Lake Tawakoni and the Lake Fork raw water supply to meet the current city needs and future water demands

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Water Construction Fund - $121,442.00 ($118,442.00, plus closing costs and title expenses not to exceed $3,000.00)

 

OWNER

 

Garland W. Martin

 

MAP

 

Attached