File #: 19-1926    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 11/21/2019 In control: Water Utilities Department
On agenda: 1/22/2020 Final action: 1/22/2020
Title: Authorize a construction contract for the installation of water and wastewater mains at 6 locations (list attached to the Agenda Information Sheet) - SYB Construction Company, Inc., lowest responsible bidder of five - Not to exceed $4,293,456.25 - Financing: Water (Drinking Water) - TWDB 2019 Fund ($2,511,641.15) and Wastewater (Clean Water) - TWDB 2019 Fund ($1,781,815.10)
Indexes: 13, 14, 2, 9
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 22, 2020
COUNCIL DISTRICT(S): 2, 9, 13, 14
DEPARTMENT: Water Utilities Department
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

title
Authorize a construction contract for the installation of water and wastewater mains at 6 locations (list attached to the Agenda Information Sheet) - SYB Construction Company, Inc., lowest responsible bidder of five - Not to exceed $4,293,456.25 - Financing: Water (Drinking Water) - TWDB 2019 Fund ($2,511,641.15) and Wastewater (Clean Water) - TWDB 2019 Fund ($1,781,815.10)

body
BACKGROUND

This action authorizes a construction contract for the replacement and rehabilitation of approximately 9,173 feet of water and wastewater mains. This includes the installation of approximately 4,537 feet of 8-inch and 822 feet of 12-inch water mains, and approximately 2,163 feet of 8-inch, 1,260 feet of 10-inch, and 391 feet of 24-inch wastewater mains.
The existing water and wastewater mains were built between 1900 and 1962. These mains are contributing to an increase in maintenance costs as well as service interruptions. The installation of the proposed segments will improve the capacity of the water and wastewater systems and reduce maintenance costs.
The following chart illustrates SYB Construction Company, Inc.'s contractual activities with the City of Dallas for the past three years:

PBW DWU PKR

Projects Completed|99910|Change Orders|99910|Projects Requiring Liquidated Damages|99910|Projects Completed by Bonding Company|99910|



ESTIMATED SCHEDULE OF PROJECT

Begin Construction March 2020
Complete Construction September 2021