Title: Authorize Supplemental Agreement No. 1 to the professional services contract with Freese and Nichols, Inc. for additional services including electrical re-design, entry signage design, public art installation coordination, increased project management, project and bid phasing services, additional construction management and traffic signal modifications at pedestrian crossings for the Dallas Love Field Entry Road - Not to exceed $331,400.00, from $1,095,000.00 to $1,426,400.00 - Financing: Aviation Construction Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     February 12, 2020

COUNCIL DISTRICT(S):                     2

DEPARTMENT:                     Department of Aviation

EXECUTIVE:                     Kimberly Bizor Tolbert

______________________________________________________________________

SUBJECT

 

Title

Authorize Supplemental Agreement No. 1 to the professional services contract with Freese and Nichols, Inc. for additional services including electrical re-design, entry signage design, public art installation coordination, increased project management, project and bid phasing services, additional construction management and traffic signal modifications at pedestrian crossings for the Dallas Love Field Entry Road - Not to exceed $331,400.00, from $1,095,000.00 to $1,426,400.00 - Financing:  Aviation Construction Fund

 

Body

BACKGROUND

 

The 2015 Dallas Love Field, Airport Master Plan Update adopted by City Council identified several strategic development programs for safe, efficient, economically vibrant and responsive operations of the airport. The Dallas Love Field Entry Road was one of several projects undertaken in response to the recommendations in the Airport Master Plan Update.

 

The project will install enhanced pedestrian pathways, landscaping, street and pedestrian lighting, and signage along Herb Kelleher Way, which is the entry road to the airport. Improvements will also include installation of major public art sculpture as a placemaking symbol of the airport.

 

On April 11, 2018, City Council authorized a professional services contract with Freese and Nichols, Inc. for design and engineering services for improvements to the Dallas Love Field Entry Road, in an amount not to exceed $1,095,000.00, by Resolution No. 18-0517.

 

This action will authorize Supplemental Agreement No. 1 to the professional services contract with Freese and Nichols, Inc. for additional services beyond the scope of the original contract, including, but not limited to:

 

                     Additional design efforts to incorporate public art sculpture

                     Electrical engineering design efforts to install “smart” streetlights of three different heights

                     Traffic signal modifications to add pedestrian phasing at new crosswalk

                     Additional Air Space study per Federal Aviation Administration requirements

                     Signage and wayfinding features

                     Additional bid phasing services

                     Additional construction phasing services

 

ESTIMATED SCHEDULE OF PROJECT

 

Began Design                     May 2018

Complete Design                     March 2020

Begin Construction                     October 2020

Complete Construction                     November 2021

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

On April 11, 2018, City Council authorized a professional services contract with Freese and Nichols, Inc. for design and engineering services for improvements to the Dallas Love Field Entry Road by Resolution No. 18-0517.

 

FISCAL INFORMATION

 

Fund

FY 2020

FY 2021

Future Years

Aviation Construction Fund

$331,400.00

$0.00

$0.00

 

Original Contract                                          $1,095,000.00

Supplemental Agreement No. 1 (this action)                                          $   331,400.00

 

Total Contract Cost                                          $1,426,400.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$331,400.00

Architectural & Engineering

25.66%

25.66%

$85,040.00

This contract meets the M/WBE goal.

Supplemental Agreement No. 1 - 27.18% Overall M/WBE participation

 

OWNER

 

Freese and Nichols, Inc.

 

Chris Bosco, P.E., Vice President

 