Title: Authorize an increase in the construction services contract with Big Sky Construction Co., Inc. for the Phase 2 Aquatics Facilities Project to add increased scope of work to elements of the original facility to include resurfacing and repairs of the existing slides and play structures and repairs to the existing filtration system at Bahama Beach Waterpark located at 1895 Campfire Circle - Not to exceed $484,666.19, from $14,652,011.75 to $15,136,677.94 - Financing: Recreation Program Fund
Indexes: 3
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life
AGENDA DATE: February 26, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with Big Sky Construction Co., Inc. for the Phase 2 Aquatics Facilities Project to add increased scope of work to elements of the original facility to include resurfacing and repairs of the existing slides and play structures and repairs to the existing filtration system at Bahama Beach Waterpark located at 1895 Campfire Circle - Not to exceed $484,666.19, from $14,652,011.75 to $15,136,677.94 - Financing: Recreation Program Fund

Body
BACKGROUND

On June 12, 2019, City Council authorized a contract with Big Sky Construction Co., Inc. for construction of the Phase 2 Aquatic Facilities Project at Bahama Beach Waterpark Expansion located at 1895 Campfire Circle, Exline Neighborhood Aquatic Center located at 2430 Eugene Street, and Harry Stone Neighborhood Aquatic Center located at 2403 Millmar Drive, in an amount not to exceed $14,580,000.00, by Resolution No. 19-0904.

On November 15, 2019, Administrative Action No. 19-1555 authorized Change Order No. 1 to the construction services contract with Big Sky Construction Co., Inc. for added scope of work for tree removal at Harry Stone Park and replacement of a water supply line at Exline Park, in an amount not to exceed $28,543.00, from $14,580,000.00 to $14,608,543.00.

On December 10, 2019, Administrative Action No. 20-0051 authorized Change Order No. 2 to the construction services contract with Big Sky Construction Co., Inc. for added scope of work for plumbing revisions at Bahama Beach Waterpark, plumbing revisions, credit for signage revisions and upgraded fencing at Exline Park, and plumbing revisions at Harry Stone Park, in an amount not to exceed $43,468.75, from $14,608,543.00 to $14,652,011.75.





This a...