Dallas Logo
File #: 20-596    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved as an Individual Item
File created: 3/20/2020 In control: Department of Public Works
On agenda: 5/13/2020 Final action: 5/13/2020
Title: Authorize a professional services contract with Gee Consultants, Inc. to provide material testing services during construction of Dolphin Road and Pearl Street and construction of Street Reconstruction Group 17-5007 (list attached to the Agenda Information Sheet) - Not to exceed $94,702.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($66,551.00) and Street and Transportation Improvement Funds (2006 General Obligation Bond Fund) ($28,151.00)
Indexes: 14, 5, 7
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     May 13, 2020

COUNCIL DISTRICT(S):                     5, 7, 14

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

Title

Authorize a professional services contract with Gee Consultants, Inc. to provide material testing services during construction of Dolphin Road and Pearl Street and construction of Street Reconstruction Group 17-5007 (list attached to the Agenda Information Sheet) - Not to exceed $94,702.00 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Funds) ($66,551.00) and Street and Transportation Improvement Funds (2006 General Obligation Bond Fund) ($28,151.00)

 

Body

BACKGROUND

 

The Request for Qualifications (CIZ1728) was issued on August 27, 2018 for the 2018 Construction Material Testing Services.  The consulting firm, Gee Consultants, Inc was selected following a qualifications-based selection process in accordance with the City of Dallas procurement guidelines.

 

This action will authorize a professional services contract with Gee Consultants, Inc. for the construction material testing services during construction of Dolphin Road and Pearl Street and construction of Street Reconstruction Group 17-5007. These testing services are required to assure that the material utilized during construction is in conformance with the quality required by the project specifications.

 

Following are the locations and design costs for each project:

 

Dolphin Road, Pearl Street and Street Reconstruction Group 17-5007

 

Project                                                                                                         Council District                                          Amount

 

Dolphin Road from Spring

to Haskell Avenue/Military Parkway                     7                                                               $40,785.00

 

Donnybrook Lane from North Prairie Creek Road

to Riverway Drive                     5                                                               $11,713.00

 

Palisade Drive from North Prairie Creek Road

to Riverway Drive                     5                                                               $14,053.00

 

Pearl Street from Pacific Avenue

to Live Oak Street                                                                                                         14                                                               $28,151.00

 

ESTIMATED SCHEDULE OF PROJECT

 

Begin Testing                                           June 2020

Complete Testing                                          June 2022

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

FISCAL INFORMATION

 

Fund

FY 2020

FY 2021

Future Years

Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

$66,551.00

$0.00

$0.00

Street and Transportation Improvement Funds (2006 General Obligation Bond Fund)

$28,151.00

$0.00

$0.00

Total

$94,702.00

$0.00

$0.00

 

Council District                                          Amount

 

7                                                               $40,785.00

                     5                                                               $25,766.00

14                                                               $28,151.00

 

        Total                                                               $94,702.00

 

M/WBE INFORMATION

 

In accordance with the City’s Business Inclusion and Development Plan adopted on October 22, 2008, by Resolution No. 08-2826, as amended, the M/WBE participation on this contract is as follows:

 

Contract Amount

Category

M/WBE Goal

M/WBE %

M/WBE $

$94,702.00

Architectural & Engineering

25.66%

25.77%

$24,402.00

This contract exceeds the M/WBE goal.

 

OWNER

 

Gee Consultants, Inc.

 

Richard W. Gee, President

 

MAPS

 

Attached