Dallas Logo
File #: 20-794    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved as an Individual Item
File created: 4/16/2020 In control: Department of Public Works
On agenda: 5/13/2020 Final action: 5/13/2020
Title: Authorize a construction contract for renovation of the West Dallas Multi-Purpose Center, located at 2828 Fish Trap Road - Turner Construction Company, the best value proposer of seven proposals - Not to exceed $1,482,175.00 - Financing: City Facilities (H) Fund (2017 General Obligation Bond Fund)
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: May 13, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction contract for renovation of the West Dallas Multi-Purpose Center, located at 2828 Fish Trap Road - Turner Construction Company, the best value proposer of seven proposals - Not to exceed $1,482,175.00 - Financing: City Facilities (H) Fund (2017 General Obligation Bond Fund)

Body
BACKGROUND

On February 21, 2020, seven proposals were received for the West Dallas Multi-Purpose Center renovation. Following a qualifications-based selection process in accordance with the City of Dallas procurement guidelines, Turner Construction Company was determined to have submitted the Best Value Proposal.

This action will authorize a construction contract with Turner Construction Company for renovation of the West Dallas Multi-Purpose Center. The scope of work includes an approximate 12,000 square foot interior renovation along with limited exterior improvements necessary for the Americans with Disabilities Act compliance.

Deferral of this item would delay the project's start and completion dates for this renovation project. This facility has various water infiltration areas where water continues to filter through the roof access doors resulting in water damage. This construction work identified will mitigate the water infiltration for this facility to be functional for future events. The postponement of awarding this construction contract will increase project costs due to either inflationary factor or contractors requiring additional compensation for delayed implementation. As a result, the project will require re-scoping and/or additional value engineering to award within budget.

ESTIMATED SCHEDULE OF PROJECT

Begin Construction June 2020
Complete Construction Janu...